Pre-posession - Salmon colored trim and closet doors, green carpet - a perfect match.

 

Pre-posession - This room has since been gutted. Pictures to come soon.

 

February 21st, 2009 - After 6 months working on the upstairs, I am finally working on the basement. Lower portions of...

 

Severe mold and nearly complete disintegration of the sill plate on the west wall will require replacement. Wall has to be...

 

August 2009 - Mold remediation is complete, sill places have been replaced, and sheetrock is up, mudded.

 

August 2009 - Mudding and sanding is getting tiring. There have been a couple nights ending after 3 AM to finish the coats...

 

October 20, 2009 - Walls are primed, ready for paint. French drain concrete was removed and repoured to prepare for floor...

 

October 25, 2009 - Concrete has been ground clean, ready for leveling compound.

 

January 6, 2010 - Huge progress in the last few weeks - Tile's down, grouted, sealed, trim is up, and a new box has been...

 

January 6, 2010 - Still left to do of course is sand and paint the old trim, which will be that touch that really brings...

 

January 17th, 2010 - Office furniture moved in. Still need to paint some of the trim.

 

January 17th, 2010 - Storage installed in closet.

 